Seguin’s four priority drainage projects

Seguin, TX, USA / Seguin Today
Seguin's four priority drainage projects


Walnut Branch Drainage Improvements

• Land acquisitions to expand the existing detention ponds near Interstate 10 and Huber Rd (north basin) and Fleming Drive (south basin)

• Build bridge crossings on San Antonio Avenue at Walnut Branch and William Street at Walnut Branch and replace low water crossing further downstream

• Construct a small drainage system on Aldama at Kingsbury for a neighborhood access road North

Heideke Street Drainage Improvements

• Create an underground storm water conveyance system on the northern end of downtown Seguin bound by North Austin and Heideke Streets. The storm drainage system will allow for conveyance of stormwater runoff from the street channel to an underground conveyance system and increase the storm drainage network for a total of 6,700 LF.

Mays Creek Drainage Improvements

• Replace culverts at State Hwy 46, County Road 725, River Oaks Dr, and County Road 402 to the appropriate size for a total of 5,650 LF

• Construct an additional driveway to ensure residential safety by allowing two ingress/egress points during flooding

North Guadalupe Street Drainage Improvements

• Install a regional detention basin via land acquisition near Guadalupe Street and FM 78

• Install a new storm drain system that will include a storm trunk line along 8th Street to West New Braunfels Street, a storm drain branch to extend east and west along West New Braunfels, a branch with inlets will extend east from 8th Street along Collins Avenue to Guadalupe Street, and a smaller branch to extend west along Kingsbury Street, for a total 11,175 LF.